Project Timeline
The expectation is that the project will take approximately 6 months for the infrastructure improvements and a further 12 months to migrate the relevant groups.
Below is the timeline detailing the projects progress.
If you would like further information on any of these elements please contact the project manager - Kodwo Intsiful.
-
February 28, 2019
Network infrastructure upgrade (switches and hardware encryption devices)
-
March 31, 2019
Backup storage and data archiving
-
April 30, 2019
Hypervisor
-
May 31, 2019
Replacement storage for file and block (100TB NetApp)
-
May 31, 2019
Replacement storage for file and block
-
June 30, 2019
Back up media
-
June 30, 2019
IAM Software (RSA Data Access Governance)
-
June 30, 2019
Project end date